Plant Integrity & Life Assessment

단계
Technical Review and Development of Inspection Plan
Pre-inform :

Drawings & O/M Manual, Operating DCS Data, Water and Steam Chemistry Control Data, Pressure Parts and Others Failure and Repair History,
Previous Inspection Report, etc.

Deliverables :

DTechnical Review pre-outage Report with High potential failure parts Detail inspection Plan

Site Inspection, Test and Assessment
Activity :

Visual Inspection, NDT, Metallurgical condition Assessment, Chemistry Assessment

Deliverables :

Exclusive Inspection and Test Report with followings,
- Current condition in terms of integrity of pressure and non-pressure parts
- Potential problem area identification such as FAC, corrosion,
  erosion, SH exfoliation, etc.
- Recommendable operation condition – operating rate and chemistry control
- Recommendations for repair and modification method with RCA

단계
단계
Total Technical Service for Repair and Modification Work according to Step 2 recommendations.
Activity :

- Site survey with Dwg and Field condition check
- Feasibility and Case study

Deliverables :

- Repair and modification Procedure with Expected Period
- Replacement material fabrication drawing with BOM
- Replacement material supply as order

Technical Assistance during Site Repair and Modification Work
Activity :

Visual Inspection, NDT, Metallurgical condition Assessment, Chemistry Assessment

Deliverables :

- Experienced special engineer mobilization as TA
- Work completion Report